Novarly ParcelRenewable sites

Renewable sitesIron Mountain Site

Iron Mountain Site

Iron Mountain Site is operational in Dacorum with a recorded capacity of 0.3 MW, and has been generating since 2020-01-01.

0.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-01-01
Solar Photovoltaics
Technology
Iron Mountain
Dacorum
Authority
England

Planning and build timeline

Application submitted2019-02-25
Permission granted2019-04-17
2 months after submission
Operational2020-01-01
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dacorum’s record on solar

Dacorum has decided 12 solar farms and approved 92%, taking a median of 1.8 months. See every solar farm decision in Dacorum

Other built sites within 15 km

SiteMWDistance
Woodside Leisure Centre - Solar PV Panels
Solar Photovoltaics · Operational
0.299.2 km
Caddington Solar Farm (Phase 2)
Solar Photovoltaics · Operational
59.8 km
Caddington Solar Farm (Phase 1)
Solar Photovoltaics · Operational
310.2 km
Aylett Nurseries - Solar Panels
Solar Photovoltaics · Operational
10.8 km
Land North of Chiltern Greeen
Solar Photovoltaics · Operational
512.5 km
Ld At Lawrence End Park &, Dane Street
Solar Photovoltaics · Operational
513.4 km
Coursers Farm AD Plant (Waste AD)
Anaerobic Digestion · Operational
314.3 km
Computacenter Warehouse
Solar Photovoltaics · Under Construction
214.3 km

How big is Iron Mountain Site?

Iron Mountain Site has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Iron Mountain Site?

REPD records the operator as Iron Mountain. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Iron Mountain Site approved and built?

The application was submitted on 2019-02-25. Permission was granted on 2019-04-17, 2 months later. The site became operational on 2020-01-01, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7249.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council