Renewable sites › Innerwick Hydro
Innerwick Hydro
Innerwick Hydro is an operational 1 MW hydro scheme in Perth and Kinross, generating since 13 October 2010. Planning permission was granted on 15 October 2008, 16 months after submission. Operator of record: Shawater.
Planning and build timeline
| Application submitted | 20 June 2007 |
| Permission granted | 15 October 2008 16 months after submission |
| Operational | 13 October 2010 24 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Innerwick Hydro’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 1.2 | 7.9 km |
Small Hydro · Operational | 1.4 | 8 km |
Large Hydro · Operational | 11 | 11.7 km |
Small Hydro · Operational | 2 | 13.4 km |
Small Hydro · Operational | 4 | 14.6 km |
How big is Innerwick Hydro?
Innerwick Hydro has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Innerwick Hydro?
REPD records the operator as Shawater. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Innerwick Hydro approved and built?
The application was submitted on 20 June 2007. Permission was granted on 15 October 2008, 16 months later. The site became operational on 13 October 2010, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 472.