Novarly ParcelRenewable sites

Renewable sitesInnerwick Hydro

Innerwick Hydro

Innerwick Hydro is an operational 1 MW hydro scheme in Perth and Kinross, generating since 13 October 2010. Planning permission was granted on 15 October 2008, 16 months after submission. Operator of record: Shawater.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 13 October 2010
Small Hydro
Technology
Shawater
Perth and Kinross
Authority
Scotland

Planning and build timeline

Application submitted20 June 2007
Permission granted15 October 2008
16 months after submission
Operational13 October 2010
24 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Perth and Kinross: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Innerwick Hydro’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
1.27.9 km
Small Hydro · Operational
1.48 km
Large Hydro · Operational
1111.7 km
Small Hydro · Operational
213.4 km
Small Hydro · Operational
414.6 km

How big is Innerwick Hydro?

Innerwick Hydro has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Innerwick Hydro?

REPD records the operator as Shawater. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Innerwick Hydro approved and built?

The application was submitted on 20 June 2007. Permission was granted on 15 October 2008, 16 months later. The site became operational on 13 October 2010, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 472.

Novarly Parcel · official public data, read properly · parcel.novarly.com