Dudgeon East� is an operational 402 MW offshore wind farm in DECC (S36), generating since 15 October 2017. Planning permission was granted on 6 July 2012, 37 months after submission. Operator of record: Statoil / Statkraft.
Planning and build timeline
| Application submitted | 12 June 2009 |
| Permission granted | 6 July 2012 37 months after submission |
| Operational | 15 October 2017 63 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dudgeon East�’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
- Special Protection Area — Greater Wash
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Offshore · Operational | 289.8 | 2.6 km |
Wind Offshore · Operational | 283.5 | 2.6 km |
Wind Offshore · Operational | 210 | 4.1 km |
Wind Offshore · Operational | 270 | 10.7 km |
Wind Offshore · Operational | 97.2 | 11 km |
Wind Offshore · Operational | 97.2 | 13.6 km |
How big is Dudgeon East�?
Dudgeon East� has a recorded installed capacity of 402 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dudgeon East�?
REPD records the operator as Statoil / Statkraft. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dudgeon East� approved and built?
The application was submitted on 12 June 2009. Permission was granted on 6 July 2012, 37 months later. The site became operational on 15 October 2017, 63 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2538.