Novarly ParcelRenewable sites

Renewable sitesWestermost Rough A

Westermost Rough A

Westermost Rough A is an operational 210 MW offshore wind farm in DECC (S36), generating since 26 May 2015. Planning permission was granted on 29 November 2011, 24 months after submission. Operator of record: Orsted (formerly Dong Energy).

210 MW
Capacity
as recorded in REPD
Operational
Status
since 26 May 2015
Wind Offshore
Technology
Orsted (formerly Dong Energy)
DECC (S36)
Authority
England

Planning and build timeline

Application submitted17 November 2009
Permission granted29 November 2011
24 months after submission
Operational26 May 2015
42 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Westermost Rough A’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Operational
4024.1 km
Wind Offshore · Operational
289.84.6 km
Wind Offshore · Operational
283.54.6 km
Wind Offshore · Operational
97.28.5 km
Wind Offshore · Operational
27010.5 km
Wind Offshore · Operational
97.212.7 km

How big is Westermost Rough A?

Westermost Rough A has a recorded installed capacity of 210 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Westermost Rough A?

REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Westermost Rough A approved and built?

The application was submitted on 17 November 2009. Permission was granted on 29 November 2011, 24 months later. The site became operational on 26 May 2015, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2545.