Renewable sites › Westermost Rough A
Westermost Rough A
Westermost Rough A is operational in DECC (S36) with a recorded capacity of 210 MW, and has been generating since 2015-05-26.
Planning and build timeline
| Application submitted | 2009-11-17 |
| Permission granted | 2011-11-29 24 months after submission |
| Operational | 2015-05-26 42 months after consent |
What this site sits on
- Special Protection Area — Greater Wash
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dudgeon East� Wind Offshore · Operational | 402 | 4.1 km |
Race Bank (Phase 1) Wind Offshore · Operational | 289.8 | 4.6 km |
Race Bank (Phase 2) Wind Offshore · Operational | 283.5 | 4.6 km |
Lynn Wind Offshore · Operational | 97.2 | 8.5 km |
Centrica (Lincs) Wind Offshore · Operational | 270 | 10.5 km |
Inner Dowsing� Wind Offshore · Operational | 97.2 | 12.7 km |
How big is Westermost Rough A?
Westermost Rough A has a recorded installed capacity of 210 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Westermost Rough A?
REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Westermost Rough A approved and built?
The application was submitted on 2009-11-17. Permission was granted on 2011-11-29, 24 months later. The site became operational on 2015-05-26, 42 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2545.