Renewable sites › Centrica (Lincs)
Centrica (Lincs)
Centrica (Lincs) is an operational 270 MW offshore wind farm in DECC (S36), generating since 24 July 2013. Planning permission was granted on 21 October 2008, 21 months after submission. Operator of record: �rsted.
Planning and build timeline
| Application submitted | 24 January 2007 |
| Permission granted | 21 October 2008 21 months after submission |
| Operational | 24 July 2013 57 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Centrica (Lincs)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
- Special Area of Conservation — Inner Dowsing, Race Bank and North Ridge
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Offshore · Operational | 97.2 | 3.5 km |
Wind Offshore · Operational | 97.2 | 6.2 km |
Wind Offshore · Operational | 289.8 | 8.1 km |
Wind Offshore · Operational | 283.5 | 8.1 km |
Wind Offshore · Operational | 210 | 10.5 km |
Wind Offshore · Operational | 402 | 10.7 km |
Solar Photovoltaics · Operational | 4.9 | 13.9 km |
How big is Centrica (Lincs)?
Centrica (Lincs) has a recorded installed capacity of 270 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Centrica (Lincs)?
REPD records the operator as �rsted. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Centrica (Lincs) approved and built?
The application was submitted on 24 January 2007. Permission was granted on 21 October 2008, 21 months later. The site became operational on 24 July 2013, 57 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2513.