Denhill is an operational 2.3 MW onshore wind farm in Aberdeenshire, generating since 1 June 2011. Planning permission was granted on 5 June 2009, 33 months after submission. Operator of record: Private Developer.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2011
Wind Onshore
Technology
Private Developer
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted15 September 2006
Permission granted5 June 2009
33 months after submission
Operational1 June 2011
24 months after consent

Screening a site of your own?

RedlineUK · £39

Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Denhill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
3.20.9 km
Wind Onshore · Operational
2.42 km
Wind Onshore · Operational
4.62.8 km
Solar Photovoltaics · Operational
1.84.7 km
Wind Onshore · Operational
25 km
Wind Onshore · Operational
2.55 km
Wind Onshore · Operational
2.35.3 km
Wind Onshore · Operational
126.2 km

How big is Denhill?

Denhill has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Denhill?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Denhill approved and built?

The application was submitted on 15 September 2006. Permission was granted on 5 June 2009, 33 months later. The site became operational on 1 June 2011, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3403.