Novarly ParcelRenewable sites

Renewable sitesHigher Knapp Farm

Higher Knapp Farm

Higher Knapp Farm is an operational 1.5 MW solar farm in Somerset, generating since 21 March 2013. Planning permission was granted on 11 January 2013, 3 months after submission. Operator of record: Lightsource Renewable Energy.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 21 March 2013
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Somerset
Authority
England

Planning and build timeline

Application submitted8 October 2012
Permission granted11 January 2013
3 months after submission
Operational21 March 2013
2 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Higher Knapp Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.22.6 km
Solar Photovoltaics · Operational
1.57 km
Solar Photovoltaics · Operational
510 km
Solar Photovoltaics · Operational
510.1 km
EfW Incineration · Under Construction
7.810.2 km
Solar Photovoltaics · Operational
510.7 km
Battery · Operational
3011.1 km
Solar Photovoltaics · Operational
511.3 km

How big is Higher Knapp Farm?

Higher Knapp Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Higher Knapp Farm?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Higher Knapp Farm approved and built?

The application was submitted on 8 October 2012. Permission was granted on 11 January 2013, 3 months later. The site became operational on 21 March 2013, 2 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1450.

Novarly Parcel · official public data, read properly · parcel.novarly.com