Novarly ParcelRenewable sites

Renewable sitesHeathfield 'A' Landfill

Heathfield 'A' Landfill

Heathfield 'A' Landfill is an operational 2 MW landfill gas site in Teignbridge, generating since 16 June 2003. Planning permission was granted on 31 March 2003, 3 months after submission. Operator of record: Viridor.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 16 June 2003
Landfill Gas
Technology
Viridor
Teignbridge
Authority
England

Planning and build timeline

Application submitted13 January 2003
Permission granted31 March 2003
3 months after submission
Operational16 June 2003
3 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Teignbridge: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Heathfield 'A' Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Operational
132.6 km
Anaerobic Digestion · Operational
28.4 km
Solar Photovoltaics · Operational
410 km
Anaerobic Digestion · Under Construction
11.6 km
Solar Photovoltaics · Operational
512 km
Solar Photovoltaics · Operational
6.512 km
Anaerobic Digestion · Operational
112.4 km
Solar Photovoltaics · Operational
812.6 km

How big is Heathfield 'A' Landfill?

Heathfield 'A' Landfill has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Heathfield 'A' Landfill?

REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Heathfield 'A' Landfill approved and built?

The application was submitted on 13 January 2003. Permission was granted on 31 March 2003, 3 months later. The site became operational on 16 June 2003, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 668.

Novarly Parcel · official public data, read properly · parcel.novarly.com