Novarly ParcelRenewable sites

Renewable sitesHarn Hill Quarry Landfill Site

Harn Hill Quarry Landfill Site

Harn Hill Quarry Landfill Site is an operational 2.6 MW landfill gas site in South Gloucestershire, generating since 1 October 1996. Planning permission was granted on 25 September 1995, 3 months after submission. Operator of record: Biogas Technology Ltd and Avon CC.

2.6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 1996
Landfill Gas
Technology
Biogas Technology Ltd and Avon CC
South Gloucestershire
Authority
England

Planning and build timeline

Application submitted6 July 1995
Permission granted25 September 1995
3 months after submission
Operational1 October 1996
12 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Gloucestershire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Harn Hill Quarry Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.64.6 km
Solar Photovoltaics · Operational
84.9 km
Solar Photovoltaics · Operational
3.55.5 km
Wind Onshore · Operational
6.96.7 km
EfW Incineration · Operational
326.9 km
Solar Photovoltaics · Operational
57 km
Solar Photovoltaics · Operational
157.1 km
Solar Photovoltaics · Operational
1.87.4 km

How big is Harn Hill Quarry Landfill Site?

Harn Hill Quarry Landfill Site has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Harn Hill Quarry Landfill Site?

REPD records the operator as Biogas Technology Ltd and Avon CC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Harn Hill Quarry Landfill Site approved and built?

The application was submitted on 6 July 1995. Permission was granted on 25 September 1995, 3 months later. The site became operational on 1 October 1996, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 722.