Novarly ParcelRenewable sites

Renewable sitesGreat Houndbeare Farm

Great Houndbeare Farm

Great Houndbeare Farm is an operational 10 MW solar farm in East Devon, generating since 31 March 2017. Planning permission was granted on 18 November 2013, 4 months after submission. Operator of record: Sunsave 49 SPV (prev. Cherry Solar).

10 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2017
Solar Photovoltaics
Technology
Sunsave 49 SPV (prev. Cherry Solar)
East Devon
Authority
England

Planning and build timeline

Application submitted5 July 2013
Permission granted18 November 2013
4 months after submission
Operational31 March 2017
40 months after consent

Screening a site of your own?

RedlineUK · £39

East Devon approves 87% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Great Houndbeare Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
300.6 km
Solar Photovoltaics · Operational
4.81.6 km
Solar Photovoltaics · Operational
12.54.8 km
Solar Photovoltaics · Operational
74.9 km
Anaerobic Digestion · Operational
15 km
Solar Photovoltaics · Operational
55.9 km
Anaerobic Digestion · Operational
26.9 km
Solar Photovoltaics · Under Construction
498.1 km

How big is Great Houndbeare Farm?

Great Houndbeare Farm has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Great Houndbeare Farm?

REPD records the operator as Sunsave 49 SPV (prev. Cherry Solar). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Great Houndbeare Farm approved and built?

The application was submitted on 5 July 2013. Permission was granted on 18 November 2013, 4 months later. The site became operational on 31 March 2017, 40 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1484.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode