Fullabrook Down Wind Farm

Fullabrook Down Wind Farm is operational in North Devon with a recorded capacity of 66 MW, and has been generating since 2012-01-24.

66 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-01-24
Wind Onshore
Technology
Devon Wind Power Ltd
North Devon
Authority
England

Planning and build timeline

Application submitted2004-10-18
Permission granted2007-10-10
36 months after submission
Operational2012-01-24
51 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Devon’s record on onshore wind

North Devon has decided 6 onshore wind schemes and approved 33%, taking a median of 26.1 months. See every onshore wind scheme decision in North Devon

Other built sites within 15 km

SiteMWDistance
West Hill Farm
Solar Photovoltaics · Operational
2.42.1 km
Blatchworthy Farm
Solar Photovoltaics · Operational
1.52.7 km
West Hill Farm (solar)
Solar Photovoltaics · Operational
7.32.7 km
Barton Close Farm
Solar Photovoltaics · Operational
5.55 km
Pall Europe Building
Solar Photovoltaics · Operational
0.585.2 km
Luscott Barton
Solar Photovoltaics · Operational
135.3 km
Exeter Road, Braunton - Solar Panels
Solar Photovoltaics · Under Construction
0.757.5 km
Perrigo,Wrafton - Solar Photovoltaic System
Solar Photovoltaics · Operational
0.537.5 km

How big is Fullabrook Down Wind Farm?

Fullabrook Down Wind Farm has a recorded installed capacity of 66 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Fullabrook Down Wind Farm?

REPD records the operator as Devon Wind Power Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Fullabrook Down Wind Farm approved and built?

The application was submitted on 2004-10-18. Permission was granted on 2007-10-10, 36 months later. The site became operational on 2012-01-24, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4033.