Renewable planning › Onshore wind › North Devon
Onshore wind planning in North Devon
North Devon has decided 6 onshore wind schemes and approved 33% of them, taking a median of 26.1 months to decide. Consented capacity: 84 MW.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How North Devon compares
Against the 75 UK authorities with 5+ onshore wind decisions, North Devon sits in the 6th percentile for approval rate (35 points below the England average) and the 9th percentile for speed.
Every recorded scheme (9)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Fullabrook Farm Wind Turbine Messrs N & K A Tucker · 57572 | 2 | Application Withdrawn | 2014-09-01 |
HOLLAMOOR FARM (wind) Private Developer · 57728 | 1.5 | Application Withdrawn | 2014-08-21 |
Batsworthy Cross Blackrock Real Assets · 43272 · 71.1 mo to decide | 18 | Operational | 2012-10-22 |
Cross Moor Devon Light and Power · 43580 · 62.8 mo to decide | 4 | Application Refused | 2012-03-16 |
Great Shelfin Farm British Telecom · 49825 | 6.9 | Application Withdrawn | 2012-01-24 |
Three Moors Wind Farm Airtricity Developments (UK) Limited · 45489 · 10 mo to decide | 22 | Appeal Refused | 2008-09-04 |
Fullabrook Down Wind Farm Devon Wind Power Ltd · 38622 · 35.7 mo to decide | 66 | Operational | 2007-10-10 |
Hore Down Windfarm Farm Energy · 29678 · 16.6 mo to decide | 2.2 | Application Refused | 2001-12-19 |
The Old Racecourse THE OLD RACECOURSE WINDFARM LTD · 29679 · 16.6 mo to decide | 2.2 | Application Refused | 2001-12-18 |
Does North Devon approve onshore wind schemes?
Yes — of the 6 onshore wind schemes North Devon has decided, 33% were approved (2 granted, 4 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in North Devon?
The median time from application to decision is 26.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has North Devon consented?
84 MW has been consented across 2 approved schemes, with 30 MW refused. There are no applications currently awaiting a decision.
Other technologies in North Devon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.