Novarly ParcelRenewable planning

Renewable planning Onshore windNorth Devon

Onshore wind planning in North Devon

North Devon has decided 6 onshore wind schemes and approved 33% of them, taking a median of 26.1 months to decide. Consented capacity: 84 MW.

33%
Approved
2 granted · 4 refused
26.1 mo
Median decision
UK 11.5 mo
84 MW
Consented
30 MW refused
2
Appeals
1 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How North Devon compares

Against the 75 UK authorities with 5+ onshore wind decisions, North Devon sits in the 6th percentile for approval rate (35 points below the UK average) and the 9th percentile for speed.

Screening a site of your own?

RedlineUK · £39

North Devon approves 33% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site£39
Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Every recorded scheme (9)

SchemeMWStatusDecided
Fullabrook Farm Wind Turbine
Messrs N & K A Tucker · 57572
2Application Withdrawn2014-09-01
HOLLAMOOR FARM (wind)
Private Developer · 57728
1.5Application Withdrawn2014-08-21
Batsworthy Cross
Blackrock Real Assets · 43272 · 71.1 mo to decide
18Operational2012-10-22
Cross Moor
Devon Light and Power · 43580 · 62.8 mo to decide
4Application Refused2012-03-16
Great Shelfin Farm
British Telecom · 49825
6.9Application Withdrawn2012-01-24
Three Moors Wind Farm
Airtricity Developments (UK) Limited · 45489 · 10 mo to decide
22Appeal Refused2008-09-04
Fullabrook Down Wind Farm
Devon Wind Power Ltd · 38622 · 35.7 mo to decide
66Operational2007-10-10
Hore Down Windfarm
Farm Energy · 29678 · 16.6 mo to decide
2.2Application Refused2001-12-19
The Old Racecourse
THE OLD RACECOURSE WINDFARM LTD · 29679 · 16.6 mo to decide
2.2Application Refused2001-12-18

Does North Devon approve onshore wind schemes?

Yes — of the 6 onshore wind schemes North Devon has decided, 33% were approved (2 granted, 4 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in North Devon?

The median time from application to decision is 26.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has North Devon consented?

84 MW has been consented across 2 approved schemes, with 30 MW refused. There are no applications currently awaiting a decision.

Other technologies in North Devon

Solar in North DevonBattery storage in North Devon

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · Coal mining search by postcode