Renewable sites › Pall Europe Building
Pall Europe Building
Pall Europe Building is an operational 0.58 MW solar farm in North Devon, generating since 15 August 2021. Planning permission was granted on 9 December 2019, 5 months after submission. Operator of record: Ivy Link Partnership.
Planning and build timeline
| Application submitted | 27 June 2019 |
| Permission granted | 9 December 2019 5 months after submission |
| Operational | 15 August 2021 20 months after consent |
Screening a site of your own?
North Devon approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pall Europe Building’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Devon’s record on solar
North Devon has decided 23 solar farms and approved 96%, taking a median of 4.9 months. See every solar farm decision in North Devon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 66 | 5.2 km |
Solar Photovoltaics · Operational | 2.4 | 5.6 km |
Solar Photovoltaics · Operational | 1.5 | 6.1 km |
Solar Photovoltaics · Operational | 7.3 | 6.1 km |
Solar Photovoltaics · Operational | 5.5 | 6.1 km |
Solar Photovoltaics · Operational | 13 | 10.1 km |
Solar Photovoltaics · Operational | 0.53 | 11.7 km |
Solar Photovoltaics · Under Construction | 0.75 | 11.7 km |
How big is Pall Europe Building?
Pall Europe Building has a recorded installed capacity of 0.58 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pall Europe Building?
REPD records the operator as Ivy Link Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pall Europe Building approved and built?
The application was submitted on 27 June 2019. Permission was granted on 9 December 2019, 5 months later. The site became operational on 15 August 2021, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7478.