Renewable sites › Fairfield Farm
Fairfield Farm
Fairfield Farm is an operational 6.5 MW onshore wind farm in Cumberland, generating since 2 March 2011. Planning permission was granted on 20 May 2008, 20 months after submission. Operator of record: Windprospect.
Planning and build timeline
| Application submitted | 29 September 2006 |
| Permission granted | 20 May 2008 20 months after submission |
| Operational | 2 March 2011 33 months after consent |
Screening a site of your own?
Cumberland approves 66% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Fairfield Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on onshore wind
Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6 | 2.9 km |
Landfill Gas · Operational | 1.8 | 2.9 km |
Landfill Gas · Operational | 1.9 | 3.6 km |
Wind Onshore · Operational | 4.7 | 3.9 km |
Solar Photovoltaics · Operational | 5 | 4 km |
Wind Onshore · Operational | 8.8 | 5.7 km |
Wind Onshore · Operational | 6 | 7.2 km |
Battery · Operational | 10 | 8.4 km |
How big is Fairfield Farm?
Fairfield Farm has a recorded installed capacity of 6.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fairfield Farm?
REPD records the operator as Windprospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fairfield Farm approved and built?
The application was submitted on 29 September 2006. Permission was granted on 20 May 2008, 20 months later. The site became operational on 2 March 2011, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3613.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode