Renewable sites › Easter Tulloch Wind Farm (Tullo Extension)
Easter Tulloch Wind Farm (Tullo Extension)
Easter Tulloch Wind Farm (Tullo Extension) is operational in Aberdeenshire with a recorded capacity of 25 MW, and has been generating since 2014-06-30.
Planning and build timeline
| Application submitted | 2011-08-09 |
| Permission granted | 2012-09-21 13 months after submission |
| Operational | 2014-06-30 21 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
BROWNIELEYS - 3 WIND TURBINES Wind Onshore · Operational | 7.5 | 1.1 km |
Tullo Wind Farm South (Ext.) Wind Onshore · Operational | 10 | 1.1 km |
Tullo Wind Farm North Extension (Shiels Wind Farm) Wind Onshore · Operational | 7.5 | 1.2 km |
Brotherton (formerly Paul Matthew Hill wind turbines) Wind Onshore · Operational | 4.6 | 2.8 km |
Macphie of Glenbervie Biomass (dedicated) · Operational | 1.2 | 8.8 km |
St. Johns Hill Wind Onshore · Operational | 7.65 | 9.5 km |
Droop Hill Wind Farm x Wind Onshore · Operational | 4.6 | 9.6 km |
St John Hill Wind Onshore · Operational | 7.7 | 9.9 km |
How big is Easter Tulloch Wind Farm (Tullo Extension)?
Easter Tulloch Wind Farm (Tullo Extension) has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Easter Tulloch Wind Farm (Tullo Extension)?
REPD records the operator as N R Gammie Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Easter Tulloch Wind Farm (Tullo Extension) approved and built?
The application was submitted on 2011-08-09. Permission was granted on 2012-09-21, 13 months later. The site became operational on 2014-06-30, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4365.