Renewable sites › Easter Tulloch Wind Farm (Tullo Extension)
Easter Tulloch Wind Farm (Tullo Extension)
Easter Tulloch Wind Farm (Tullo Extension) is an operational 25 MW onshore wind farm in Aberdeenshire, generating since 30 June 2014. Planning permission was granted on 21 September 2012, 13 months after submission. Operator of record: N R Gammie Partnership.
Planning and build timeline
| Application submitted | 9 August 2011 |
| Permission granted | 21 September 2012 13 months after submission |
| Operational | 30 June 2014 21 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Easter Tulloch Wind Farm (Tullo Extension)’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 7.5 | 1.1 km |
Wind Onshore · Operational | 10 | 1.1 km |
Wind Onshore · Operational | 7.5 | 1.2 km |
Wind Onshore · Operational | 4.6 | 2.8 km |
Biomass (dedicated) · Operational | 1.2 | 8.8 km |
Wind Onshore · Operational | 7.65 | 9.5 km |
Wind Onshore · Operational | 4.6 | 9.6 km |
Wind Onshore · Operational | 7.7 | 9.9 km |
How big is Easter Tulloch Wind Farm (Tullo Extension)?
Easter Tulloch Wind Farm (Tullo Extension) has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Easter Tulloch Wind Farm (Tullo Extension)?
REPD records the operator as N R Gammie Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Easter Tulloch Wind Farm (Tullo Extension) approved and built?
The application was submitted on 9 August 2011. Permission was granted on 21 September 2012, 13 months later. The site became operational on 30 June 2014, 21 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4365.
Novarly Parcel · official public data, read properly · parcel.novarly.com