Renewable sites › Easter Melrose Wind Energy Project
Easter Melrose Wind Energy Project
Easter Melrose Wind Energy Project is operational in Aberdeenshire with a recorded capacity of 1.5 MW, and has been generating since 2015-12-01.
Planning and build timeline
| Application submitted | 2011-08-02 |
| Permission granted | 2012-11-28 16 months after submission |
| Operational | 2015-12-01 36 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Milton of Fisherie Wind Cluster Wind Onshore · Operational | 4.6 | 4.5 km |
Gairnieston Farm Wind Onshore · Operational | 2.3 | 7.5 km |
Backhill of Yonderton Wind Cluster Wind Onshore · Operational | 4.6 | 8.2 km |
Little Byth Wind Onshore · Operational | 4.5 | 9.7 km |
Strath of Brydock - Extension Wind Onshore · Operational | 2.3 | 10.5 km |
Strath of Brydock Wind Onshore · Operational | 4.6 | 10.5 km |
Cairnhill Farm solar park Solar Photovoltaics · Operational | 2.4 | 11.5 km |
Gawnsmoss Cluster Wind Onshore · Operational | 2.4 | 12.4 km |
How big is Easter Melrose Wind Energy Project?
Easter Melrose Wind Energy Project has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Easter Melrose Wind Energy Project?
REPD records the operator as Melrose Farms. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Easter Melrose Wind Energy Project approved and built?
The application was submitted on 2011-08-02. Permission was granted on 2012-11-28, 16 months later. The site became operational on 2015-12-01, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3819.