Renewable sites › Easter Melrose Wind Energy Project
Easter Melrose Wind Energy Project
Easter Melrose Wind Energy Project is an operational 1.5 MW onshore wind farm in Aberdeenshire, generating since 1 December 2015. Planning permission was granted on 28 November 2012, 16 months after submission. Operator of record: Melrose Farms.
Planning and build timeline
| Application submitted | 2 August 2011 |
| Permission granted | 28 November 2012 16 months after submission |
| Operational | 1 December 2015 36 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Easter Melrose Wind Energy Project’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.6 | 4.5 km |
Wind Onshore · Operational | 2.3 | 7.5 km |
Wind Onshore · Operational | 4.6 | 8.2 km |
Wind Onshore · Operational | 4.5 | 9.7 km |
Wind Onshore · Operational | 2.3 | 10.5 km |
Wind Onshore · Operational | 4.6 | 10.5 km |
Solar Photovoltaics · Operational | 2.4 | 11.5 km |
Wind Onshore · Operational | 2.4 | 12.4 km |
How big is Easter Melrose Wind Energy Project?
Easter Melrose Wind Energy Project has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Easter Melrose Wind Energy Project?
REPD records the operator as Melrose Farms. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Easter Melrose Wind Energy Project approved and built?
The application was submitted on 2 August 2011. Permission was granted on 28 November 2012, 16 months later. The site became operational on 1 December 2015, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3819.