Planning and build timeline

Application submitted2013-04-02
Permission granted2013-05-31
2 months after submission
Operational2015-09-15
27 months after consent

Aberdeenshire’s record on solar

Aberdeenshire has decided 39 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Backhill of Yonderton Wind Cluster
Wind Onshore · Operational
4.64 km
Bogenlea Farm
Wind Onshore · Operational
2.34.4 km
Gairnieston Farm
Wind Onshore · Operational
2.34.8 km
Little Byth
Wind Onshore · Operational
4.57.2 km
Milton of Fisherie Wind Cluster
Wind Onshore · Operational
4.67.2 km
Greenhill Croft
Wind Onshore · Operational
4.610.9 km
Easter Melrose Wind Energy Project
Wind Onshore · Operational
1.511.5 km
Shielburn Farm
Wind Onshore · Operational
6.912.2 km

How big is Cairnhill Farm solar park?

Cairnhill Farm solar park has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cairnhill Farm solar park?

REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cairnhill Farm solar park approved and built?

The application was submitted on 2013-04-02. Permission was granted on 2013-05-31, 2 months later. The site became operational on 2015-09-15, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1358.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council