Renewable sites › Wally Corner Landfill Site
Wally Corner Landfill Site
Wally Corner Landfill Site is operational in South Oxfordshire with a recorded capacity of 7 MW, and has been generating since 2017-03-15.
Planning and build timeline
| Application submitted | 2015-07-22 |
| Permission granted | 2015-09-29 2 months after submission |
| Operational | 2017-03-15 18 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — South Oxfordshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Oxfordshire’s record on solar
South Oxfordshire has decided 22 solar farms and approved 95%, taking a median of 4.2 months. See every solar farm decision in South Oxfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Langley Hall Farm Solar Photovoltaics · Operational | 2.4 | 4.5 km |
EFDA JJET Fusion Flywheel Flywheels · Operational | 400 | 4.6 km |
Wallingford (Waste AD) Anaerobic Digestion · Operational | 2.4 | 5.9 km |
Crowmarsh Battle Farm (Farm AD) Anaerobic Digestion · Operational | 2.3 | 6.6 km |
Cowley electricity sub-station Battery · Operational | 49.9 | 6.9 km |
Sutton Courtney Landfill Gas · Operational | 6 | 6.9 km |
Easington Farm (Chalgrove) Solar Photovoltaics · Operational | 21.3 | 7.2 km |
Sutton Courtenay Landfill Scheme Landfill Gas · Operational | 5.6 | 7.8 km |
How big is Wally Corner Landfill Site?
Wally Corner Landfill Site has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wally Corner Landfill Site?
REPD records the operator as SBC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wally Corner Landfill Site approved and built?
The application was submitted on 2015-07-22. Permission was granted on 2015-09-29, 2 months later. The site became operational on 2017-03-15, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5551.