Renewable sites › Double Arches Quarry Wind Turbine
Double Arches Quarry Wind Turbine
Double Arches Quarry Wind Turbine is operational in Central Bedfordshire with a recorded capacity of 1.5 MW, and has been generating since 2014-12-18.
Planning and build timeline
| Application submitted | 2010-09-08 |
| Permission granted | 2011-08-02 11 months after submission |
| Operational | 2014-12-18 41 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Green Belt — Central Bedfordshire
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Central Bedfordshire’s record on onshore wind
Central Bedfordshire has decided 7 onshore wind schemes and approved 86%, taking a median of 8.6 months. See every onshore wind scheme decision in Central Bedfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Checkley Wood Farm Wind Onshore · Operational | 4.1 | 0.4 km |
Manor Farm Solar Photovoltaics · Operational | 5 | 3.4 km |
Trinity Hall Solar Farm Solar Photovoltaics · Under Construction | 15 | 5.1 km |
Tebworth - Battery Storage Battery · Under Construction | — | 5.2 km |
Tebworth - Solar Farm Solar Photovoltaics · Under Construction | — | 5.2 km |
Trinity Hall Farm Anaerobic Digestion · Operational | 1.1 | 6 km |
Goosey Lodge Industrial Estate Biomass (dedicated) · Operational | 16 | 8 km |
Church Farm Solar Photovoltaics · Operational | 6.2 | 8.9 km |
How big is Double Arches Quarry Wind Turbine?
Double Arches Quarry Wind Turbine has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Double Arches Quarry Wind Turbine?
REPD records the operator as Arnold White Estates (AWE Renewables). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Double Arches Quarry Wind Turbine approved and built?
The application was submitted on 2010-09-08. Permission was granted on 2011-08-02, 11 months later. The site became operational on 2014-12-18, 41 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4295.
Novarly Parcel · official public data, read properly · parcel.novarly.com