Novarly ParcelRenewable sites

Renewable sitesPentlow Hill

Pentlow Hill

Pentlow Hill is an operational 24 MW solar farm in Braintree, generating since 10 June 2024. Planning permission was granted on 23 April 2021, 9 months after submission. Operator of record: Nextpower SPV 11 Limited.

24 MW
Capacity
as recorded in REPD
Operational
Status
since 10 June 2024
Solar Photovoltaics
Technology
Nextpower SPV 11 Limited
Braintree
Authority
England

Planning and build timeline

Application submitted10 July 2020
Permission granted23 April 2021
9 months after submission
Operational10 June 2024
38 months after consent

Screening a site of your own?

RedlineUK · £39

Braintree approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pentlow Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Braintree’s record on solar

Braintree has decided 23 solar farms and approved 96%, taking a median of 3.6 months. See every solar farm decision in Braintree

Other built sites within 15 km

SiteMWDistance
Battery · Operational
203.9 km
Solar Photovoltaics · Under Construction
49.995 km
Solar Photovoltaics · Operational
31.611.6 km
Solar Photovoltaics · Operational
12.614.8 km

How big is Pentlow Hill?

Pentlow Hill has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pentlow Hill?

REPD records the operator as Nextpower SPV 11 Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pentlow Hill approved and built?

The application was submitted on 10 July 2020. Permission was granted on 23 April 2021, 9 months later. The site became operational on 10 June 2024, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7666.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode