Novarly ParcelRenewable sites

Renewable sitesCrockandun

Crockandun

Crockandun is an operational 15 MW onshore wind farm in Mid Ulster, generating since 9 March 2017. Planning permission was granted on 30 November 2012, 35 months after submission. Operator of record: Brookfield Renewable Energy Group.

15 MW
Capacity
as recorded in REPD
Operational
Status
since 9 March 2017
Wind Onshore
Technology
Brookfield Renewable Energy Group
Mid Ulster
Authority
Northern Ireland

Planning and build timeline

Application submitted8 January 2010
Permission granted30 November 2012
35 months after submission
Operational9 March 2017
51 months after consent

Screening a site of your own?

RedlineUK · £39

Mid Ulster approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Crockandun’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Mid Ulster’s record on onshore wind

Mid Ulster has decided 27 onshore wind schemes and approved 85%, taking a median of 21 months. See every onshore wind scheme decision in Mid Ulster

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
18.6 km
Wind Onshore · Operational
69 km
Solar Photovoltaics · Operational
4.99.8 km
Anaerobic Digestion · Operational
113.2 km

How big is Crockandun?

Crockandun has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Crockandun?

REPD records the operator as Brookfield Renewable Energy Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Crockandun approved and built?

The application was submitted on 8 January 2010. Permission was granted on 30 November 2012, 35 months later. The site became operational on 9 March 2017, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4156.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode