Dale Farm is an operational 4.9 MW solar farm in Mid Ulster, generating since 1 August 2018. Planning permission was granted on 21 January 2016, 4 months after submission. Operator of record: Solar Farm DFD.

4.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2018
Solar Photovoltaics
Technology
Solar Farm DFD
Mid Ulster
Authority
Northern Ireland

Planning and build timeline

Application submitted28 September 2015
Permission granted21 January 2016
4 months after submission
Operational1 August 2018
30 months after consent

Screening a site of your own?

RedlineUK · £39

Mid Ulster approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dale Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Mid Ulster’s record on solar

Mid Ulster has decided 8 solar farms and approved 100%, taking a median of 3.8 months. See every solar farm decision in Mid Ulster

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
13.5 km
Wind Onshore · Operational
159.8 km
Wind Onshore · Operational
114.1 km
Wind Onshore · Operational
214.6 km

How big is Dale Farm?

Dale Farm has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dale Farm?

REPD records the operator as Solar Farm DFD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dale Farm approved and built?

The application was submitted on 28 September 2015. Permission was granted on 21 January 2016, 4 months later. The site became operational on 1 August 2018, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5852.