Renewable sites › Magherafelt
Magherafelt
Magherafelt is operational in Mid Ulster with a recorded capacity of 1 MW, and has been generating since 2015-06-12.
Planning and build timeline
| Application submitted | 2009-07-15 |
| Permission granted | 2010-11-11 16 months after submission |
| Operational | 2015-06-12 55 months after consent |
Mid Ulster’s record on onshore wind
Mid Ulster has decided 27 onshore wind schemes and approved 85%, taking a median of 21 months. See every onshore wind scheme decision in Mid Ulster →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Draperstown (Brackagh) Wind Farm Wind Onshore · Operational | 6 | 6.1 km |
Crockandun Wind Onshore · Operational | 15 | 8.6 km |
Dale Farm Solar Photovoltaics · Operational | 4.9 | 14.1 km |
How big is Magherafelt?
Magherafelt has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Magherafelt?
REPD records the operator as Tobermore Concrete Products. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Magherafelt approved and built?
The application was submitted on 2009-07-15. Permission was granted on 2010-11-11, 16 months later. The site became operational on 2015-06-12, 55 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3678.