Renewable planning › Onshore wind › Mid Ulster
Onshore wind planning in Mid Ulster
Mid Ulster has decided 27 onshore wind schemes and approved 85% of them, taking a median of 21 months to decide. Consented capacity: 148 MW. 14 applications still awaiting a decision.
How Mid Ulster compares
Against the 75 UK authorities with 5+ onshore wind decisions, Mid Ulster sits in the 85th percentile for approval rate (17 points above the England average) and the 16th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (48)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wind Turbine Development in Moneymore Unkown · LA09/2025/0203/F | 0.2 | Application Submitted | 2025-02-26 |
Wind Turbine Development in Dungannon Carland Mill Ltd · LA09/2025/0027/F | — | Application Submitted | 2025-01-15 |
Wind Turbine Development in Dungannon Private Developer · LA09/2024/1109/F | — | Application Submitted | 2024-09-20 |
Gortagammon Road Replacement Turbine Arena Capital Partners Limited · LA09/2021/0268/F · 38.4 mo to decide | 0.25 | Awaiting Construction | 2024-05-02 |
Wind Turbine Development in Stewartstown Private Developer · LA09/2023/0193/F · 12.2 mo to decide | 0.66 | Awaiting Construction | 2024-02-27 |
Tannaghlane Road, Caledon - Wind Turbine SI Energy Limited · LA09/2023/1049/F | — | Application Submitted | 2023-10-04 |
Power Generation Development in Draperstown PPG Renewables Limited · LA09/2023/0429/F | — | Application Submitted | 2023-04-05 |
Drumard Road and Cullion Road - Wind Turbine PON Wind Limited · LA09/2023/0427/F | — | Application Submitted | 2023-04-05 |
Drumard Road and Cullion Road - Wind Turbine B K Energy Limited · LA09/2023/0428/F | — | Application Submitted | 2023-04-05 |
Drumard Road and Cullion Road - Wind Turbine PPG Renewables Limited · LA09/2023/0429/F | — | Application Submitted | 2023-04-05 |
Airfield Road, The Creagh Corr Limited · LA09/2021/1233/F · 15.8 mo to decide | 0.15 | Awaiting Construction | 2022-12-19 |
Beltonanean 2 Private Developer · LA09/2017/0272/F · 62.9 mo to decide | 2.3 | Planning Permission Expired | 2022-05-30 |
Sessiagh Road Arena Capital Partners Limited · LA09/2020/1305/F · 18.2 mo to decide | 0.25 | Awaiting Construction | 2022-04-26 |
Wind Turbine Development in Stewartstown Private Developer · LA09/2021/1714/F · 4.2 mo to decide | 0.15 | Awaiting Construction | 2022-04-06 |
Shantavy Scotch Brookfield Renewable · LA09/2020/0880/F · 16.8 mo to decide | 14 | Awaiting Construction | 2021-12-15 |
Corlacky Hill Wind Farm Renewable Energy Systems (RES) · LA09/2016/0232/F · 57.9 mo to decide | 36.3 | Awaiting Construction | 2021-03-16 |
Omagh Road Private Developer · LA09/2019/1344/F · 16.2 mo to decide | 0.5 | Awaiting Construction | 2021-02-19 |
Broughderg Private Developer · LA09/2020/1645/F | 0.2 | Application Submitted | 2020-12-21 |
Doraville Wind Farm Scottish and Southern Energy (SSE) · LA10/2015/0292/F · 63.7 mo to decide | 119 | Application Refused | 2020-10-26 |
Rockdale Road Private Developer · LA09/2020/0232/F | 0.3 | Application Withdrawn | 2020-10-16 |
Brockaghboy Wind Farm (Further Extension) Brockaghboy Windfarm · LA09/2019/1386/F · 10.4 mo to decide | 10 | Awaiting Construction | 2020-08-25 |
Legilly Road Arena Capital Partners · LA09/2019/1395/F · 6.2 mo to decide | 0.3 | Awaiting Construction | 2020-04-30 |
Kilsannagh Lane Arena Capital Partners · LA09/2019/1396/F · 6.2 mo to decide | 0.3 | Awaiting Construction | 2020-04-30 |
Eden Road Private Developer · LA09/2020/0203/F | 0.3 | Application Submitted | 2020-02-14 |
Tullyaran Road Private Developer · LA09/2019/0171/F · 7.1 mo to decide | 0.2 | Awaiting Construction | 2019-09-12 |
Cullion wind farm ABO Wind · LA09/2019/0990/F | 25 | Application Submitted | 2019-07-19 |
Drumard Road (repowering) PJT Power · LA09/2018/1694/F | 0.5 | Application Submitted | 2018-12-21 |
Ballynagilly Renewable Energy Project Island Renewable Energy · LA09/2015/0459/F · 34.5 mo to decide | 18.4 | Appeal Withdrawn | 2018-05-11 |
Beltonanean Wind Farm Island Renewable Energy · I/2014/0413/F · 34.2 mo to decide | 12 | Appeal Withdrawn | 2017-11-24 |
Beltonanean Wind Turbine 2 Beltonanean Renewable Energy · I/2014/0399/F · 25.8 mo to decide | 2.3 | Revised | 2017-02-08 |
Land North East And North West Of Shanmaghry Hill Power · M/2015/0092/F | 1.5 | Application Withdrawn | 2016-12-15 |
Eshmore Wind Farm Extension Energia Renewables · LA09/2015/0488/F · 12.2 mo to decide | 2.3 | Planning Permission Expired | 2016-07-08 |
Dirnan Road Wind Turbine Private Developer · I/2014/0226/F · 11.1 mo to decide | 3 | Appeal Refused | 2015-06-04 |
Slieve Beagh Airtricity · M/2003/0999/F | 30 | Application Withdrawn | 2013-10-08 |
Crockandun Brookfield Renewable Energy Group · H/2010/0009/F · 34.7 mo to decide | 15 | Operational | 2012-11-30 |
Crockbrack Gaelectric Developments/ CGN Europe Energy · I/2008/0157/F · 52.2 mo to decide | 2 | Operational | 2012-06-19 |
Beltonanean Wind Turbine Beltonanean Renewable Energy · I/2010/0211/F · 24 mo to decide | 2.3 | Revised | 2012-05-17 |
Shantavny Scotch Tyrone Wind Energy Ltd · M/2007/1407/F · 51.9 mo to decide | 16.1 | Operational | 2012-02-24 |
Eshmore Energia Renewables · M/2006/1802/F · 60.3 mo to decide | 6.9 | Operational | 2011-10-19 |
Mullynaveagh� Mullynaveagh Wind Limited� · M/2008/1327/F · 23.8 mo to decide | 4.6 | Abandoned | 2010-12-09 |
Cappagh Gaelectric Developments · M/2008/0476/F | 9 | Application Withdrawn | 2010-12-07 |
Magherafelt Tobermore Concrete Products · H/2009/0420/F · 15.9 mo to decide | 1 | Operational | 2010-11-11 |
Draperstown (Brackagh) Wind Farm Renewable Energy Generation (REG) · H/2009/0075/F · 16.6 mo to decide | 6 | Operational | 2010-06-28 |
Slatbeg DP Energy Ireland Ltd · M/2006/1754/F · 25.9 mo to decide | 20.7 | Application Refused | 2009-02-09 |
Hunter's Hill Wind Farm Developments / RES UK & Ireland · K/2005/0387/F · 45.2 mo to decide | 20 | Operational | 2008-12-01 |
Mullaghturk Mountain Unknown · H/2004/1395/F · 34 mo to decide | 10.5 | Application Refused | 2007-10-25 |
Lendrum's Bridge Wind Farm Renewable Energy Systems (RES) · 7.9 mo to decide | 5.9 | Operational | 1998-05-11 |
Lendrum's Bridge Wind Farm ( Extension 2) Renewable Energy Systems (RES) · 7.9 mo to decide | 7.3 | Operational | 1998-05-11 |
Does Mid Ulster approve onshore wind schemes?
Yes — of the 27 onshore wind schemes Mid Ulster has decided, 85% were approved (23 granted, 4 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Mid Ulster?
The median time from application to decision is 21 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Mid Ulster consented?
148 MW has been consented across 23 approved schemes, with 153 MW refused. A further 14 applications awaits a decision.
Other technologies in Mid Ulster
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.