Rheidol Wind Farm is an operational 2.4 MW onshore wind farm in Ceredigion, generating since 6 February 1997. Planning permission was granted on 6 August 1996, 60 months after submission. Operator of record: Powergen.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 6 February 1997
Wind Onshore
Technology
Powergen
Ceredigion
Authority
Wales

Planning and build timeline

Application submitted1 August 1991
Permission granted6 August 1996
60 months after submission
Operational6 February 1997
6 months after consent

Screening a site of your own?

RedlineUK · £39

Ceredigion approves 83% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Rheidol Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Ceredigion’s record on onshore wind

Ceredigion has decided 6 onshore wind schemes and approved 83%, taking a median of 14.9 months. See every onshore wind scheme decision in Ceredigion

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
58.58.6 km
Wind Onshore · Operational
10.29.1 km
Wind Onshore · Operational
16.411.6 km
Solar Photovoltaics · Operational
2.512.9 km

How big is Rheidol Wind Farm?

Rheidol Wind Farm has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Rheidol Wind Farm?

REPD records the operator as Powergen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Rheidol Wind Farm approved and built?

The application was submitted on 1 August 1991. Permission was granted on 6 August 1996, 60 months later. The site became operational on 6 February 1997, 6 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3552.