Onshore wind planning in Ceredigion

Ceredigion has decided 6 onshore wind schemes and approved 83% of them, taking a median of 14.9 months to decide. Consented capacity: 81 MW. 1 application still awaiting a decision.

83%
Approved
5 granted · 1 refused
14.9 mo
Median decision
UK 11.5 mo
81 MW
Consented
6 MW refused
1
Appeals
0 allowed on appeal

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Ceredigion compares

Against the 75 UK authorities with 5+ onshore wind decisions, Ceredigion sits in the 82nd percentile for approval rate (15 points above the England average) and the 45th percentile for speed.

Decisions by year

35Refused — 1 (2015)115Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Cambrian Cross Country, Trefilan - Wind Turbine
Aber Heating Engineers · A240850 · 9 mo to decide
0.5Awaiting Construction2025-08-21
Rhos Garn Whirlgarn
Renewable Energy Systems (RES) · A150038 · 3.4 mo to decide
6Appeal Refused2015-05-28
Rhos Garn
Renewable Energy Systems (RES) · A050648 · 15.4 mo to decide
20Revised2006-09-13
Llangwyryfon
Westbury Windfarms · A01/1330 · 14.9 mo to decide
9.4Operational2003-03-01
Cefn Croes Wind Farm
Renewable Development Company Ltd, KENTECH Ltd · AD00737 · 16.6 mo to decide
58.5Operational2001-12-10
Rheidol Wind Farm
Powergen · 60.2 mo to decide
2.4Operational1996-08-06
Mynydd Gorddu Wind Farm
Cynllun Trydan Gwynt · 8.2 mo to decide
10.2Operational1991-09-12

Does Ceredigion approve onshore wind schemes?

Yes — of the 6 onshore wind schemes Ceredigion has decided, 83% were approved (5 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Ceredigion?

The median time from application to decision is 14.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Ceredigion consented?

81 MW has been consented across 5 approved schemes, with 6 MW refused. A further 1 application awaits a decision.

Other technologies in Ceredigion

Solar in CeredigionBattery storage in Ceredigion

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.