Novarly ParcelRenewable sites

Renewable sitesCarraig Gheal

Carraig Gheal

Carraig Gheal is an operational 46 MW onshore wind farm in Scotland, generating since 28 October 2013. Planning permission was granted on 13 June 2008, 43 months after submission. Operator of record: Green Power.

46 MW
Capacity
as recorded in REPD
Operational
Status
since 28 October 2013
Wind Onshore
Technology
Green Power
National
Authority
Scotland

Planning and build timeline

Application submitted15 November 2004
Permission granted13 June 2008
43 months after submission
Operational28 October 2013
64 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Carraig Gheal’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
7.84.8 km
Pumped Storage Hydroelectricity · Operational
44013.8 km
Small Hydro · Operational
214.2 km
Wind Onshore · Operational
19.314.2 km
Small Hydro · Operational
2.214.3 km

How big is Carraig Gheal?

Carraig Gheal has a recorded installed capacity of 46 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carraig Gheal?

REPD records the operator as Green Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carraig Gheal approved and built?

The application was submitted on 15 November 2004. Permission was granted on 13 June 2008, 43 months later. The site became operational on 28 October 2013, 64 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4619.

Novarly Parcel · official public data, read properly · parcel.novarly.com