Cantelupe Solar Farm

Cantelupe Solar Farm is an operational 5 MW solar farm in South Cambridgeshire, generating since 28 February 2013. Planning permission was granted on 27 April 2011, 3 months after submission. Operator of record: Innogy (previously - Belectric (previously Alectron Investments Ltd)).

5 MW
Capacity
as recorded in REPD
Operational
Status
since 28 February 2013
Solar Photovoltaics
Technology
Innogy (previously - Belectric (previously Alectron Investments Ltd))
South Cambridgeshire
Authority
England

Planning and build timeline

Application submitted28 January 2011
Permission granted27 April 2011
3 months after submission
Operational28 February 2013
22 months after consent

Screening a site of your own?

RedlineUK · £39

South Cambridgeshire approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cantelupe Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Cambridgeshire’s record on solar

South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.48.4 km
Solar Photovoltaics · Operational
13.18.9 km
Landfill Gas · Operational
29.7 km
Solar Photovoltaics · Operational
510.2 km
Solar Photovoltaics · Operational
31.810.5 km
Solar Photovoltaics · Operational
16.511.2 km
Solar Photovoltaics · Operational
2411.2 km
Solar Photovoltaics · Operational
4511.5 km

How big is Cantelupe Solar Farm?

Cantelupe Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cantelupe Solar Farm?

REPD records the operator as Innogy (previously - Belectric (previously Alectron Investments Ltd)). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cantelupe Solar Farm approved and built?

The application was submitted on 28 January 2011. Permission was granted on 27 April 2011, 3 months later. The site became operational on 28 February 2013, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1034.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode