Renewable sites › Hoback Farm
Hoback Farm
Hoback Farm is operational in South Cambridgeshire with a recorded capacity of 13.1 MW, and has been generating since 2014-11-01.
Planning and build timeline
| Application submitted | 2013-02-14 |
| Permission granted | 2013-07-15 5 months after submission |
| Operational | 2014-11-01 16 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Cambridgeshire’s record on solar
South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lamp Hill Wimpole Estate Solar Photovoltaics · Operational | 0.4 | 1.9 km |
Vine Farm Solar Park Solar Photovoltaics · Operational | 45 | 2.9 km |
Croydon / Church Farm (Royston) Solar Photovoltaics · Operational | 16.5 | 3.6 km |
Bury Lane Fruit Farm Solar Photovoltaics · Operational | 24 | 4.9 km |
Bassingbourn Solar Farm Solar Photovoltaics · Operational | 14.4 | 5.5 km |
Royston Solar Farm (Phase 1) (a) Solar Photovoltaics · Operational | 5 | 6 km |
Munceys Farm Solar Photovoltaics · Operational | 31.6 | 6.6 km |
Black Peak Farm Solar Photovoltaics · Operational | 31.8 | 7 km |
How big is Hoback Farm?
Hoback Farm has a recorded installed capacity of 13.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hoback Farm?
REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hoback Farm approved and built?
The application was submitted on 2013-02-14. Permission was granted on 2013-07-15, 5 months later. The site became operational on 2014-11-01, 16 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1875.
Novarly Parcel · official public data, read properly · parcel.novarly.com