Bourne Farm

Bourne Farm is an operational 2.4 MW solar farm in Dorset, generating since 15 March 2015. Planning permission was granted on 14 October 2013, 2 months after submission. Operator of record: Farm Power Apollo.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2015
Solar Photovoltaics
Technology
Farm Power Apollo
Dorset
Authority
England

Planning and build timeline

Application submitted1 August 2013
Permission granted14 October 2013
2 months after submission
Operational15 March 2015
17 months after consent

Screening a site of your own?

RedlineUK · £39

Dorset approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bourne Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on solar

Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.10.2 km
Solar Photovoltaics · Operational
50.3 km
Biomass (dedicated) · Under Construction
7.3 km
Solar Photovoltaics · Under Construction
7.3 km
Large Hydro · Operational
108.3 km
Solar Photovoltaics · Operational
59.8 km
Solar Photovoltaics · Operational
511.2 km
Solar Photovoltaics · Operational
512.4 km

How big is Bourne Farm?

Bourne Farm has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bourne Farm?

REPD records the operator as Farm Power Apollo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bourne Farm approved and built?

The application was submitted on 1 August 2013. Permission was granted on 14 October 2013, 2 months later. The site became operational on 15 March 2015, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6062.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode