Renewable sites › Bogenlea Farm
Bogenlea Farm
Bogenlea Farm is operational in Aberdeenshire with a recorded capacity of 2.3 MW, and has been generating since 2014-08-18.
Planning and build timeline
| Application submitted | 2009-05-20 |
| Permission granted | 2009-12-10 7 months after submission |
| Operational | 2014-08-18 56 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Cairnhill Farm solar park Solar Photovoltaics · Operational | 2.4 | 4.4 km |
Little Byth Wind Onshore · Operational | 4.5 | 4.6 km |
Greenhill Croft Wind Onshore · Operational | 4.6 | 6.7 km |
Backhill of Yonderton Wind Cluster Wind Onshore · Operational | 4.6 | 7.4 km |
Gairnieston Farm Wind Onshore · Operational | 2.3 | 8 km |
Milton of Fisherie Wind Cluster Wind Onshore · Operational | 4.6 | 9.3 km |
Hill of Balquhindachy extension Wind Onshore · Operational | 1.7 | 11 km |
Easter Melrose Wind Energy Project Wind Onshore · Operational | 1.5 | 12.6 km |
How big is Bogenlea Farm?
Bogenlea Farm has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bogenlea Farm?
REPD records the operator as Eco2. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bogenlea Farm approved and built?
The application was submitted on 2009-05-20. Permission was granted on 2009-12-10, 7 months later. The site became operational on 2014-08-18, 56 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4346.