Renewable sites › Earl's Hall
Earl's Hall
Earl's Hall is operational in Tendring with a recorded capacity of 10.3 MW, and has been generating since 2013-01-13.
Planning and build timeline
| Application submitted | 2007-03-22 |
| Permission granted | 2009-11-19 32 months after submission |
| Operational | 2013-01-13 38 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chisbon Solar Farm (Frowick Lane) Solar Photovoltaics · Operational | 13 | 2.2 km |
Jaywick Water Recycling Centre Solar Photovoltaics · Operational | 0.9 | 2.7 km |
Bluegates Solar Park Solar Photovoltaics · Operational | 10.5 | 9.3 km |
Blue Gates Farm Wind Onshore · Operational | 1.5 | 9.5 km |
Gunfleet Sands Offshore Wind Scheme Wind Offshore · Operational | 108 | 11.4 km |
Wix Lodge Solar Photovoltaics · Operational | 18.7 | 11.6 km |
Green Farm Solar Photovoltaics · Operational | 5 | 11.8 km |
Langenhoe Solar Farm Solar Photovoltaics · Operational | 21.3 | 12 km |
How big is Earl's Hall?
Earl's Hall has a recorded installed capacity of 10.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Earl's Hall?
REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Earl's Hall approved and built?
The application was submitted on 2007-03-22. Permission was granted on 2009-11-19, 32 months later. The site became operational on 2013-01-13, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3943.
Novarly Parcel · official public data, read properly · parcel.novarly.com