Renewable sites › Langenhoe Solar Farm
Langenhoe Solar Farm
Langenhoe Solar Farm is an operational 21.3 MW solar farm in Colchester, generating since 4 March 2015. Planning permission was granted on 29 August 2014, 9 months after submission. Operator of record: NextEnergy Solar Fund.
Planning and build timeline
| Application submitted | 22 November 2013 |
| Permission granted | 29 August 2014 9 months after submission |
| Operational | 4 March 2015 6 months after consent |
Screening a site of your own?
Colchester approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Langenhoe Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Colchester’s record on solar
Colchester has decided 19 solar farms and approved 95%, taking a median of 3 months. See every solar farm decision in Colchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sewage Sludge Digestion · Operational | 1.2 | 6.9 km |
Solar Photovoltaics · Operational | 10.5 | 7 km |
Wind Onshore · Operational | 1.5 | 7.2 km |
Solar Photovoltaics · Operational | 49 | 7.2 km |
Landfill Gas · Operational | 3.9 | 9.3 km |
Solar Photovoltaics · Operational | 5 | 9.7 km |
Solar Photovoltaics · Operational | 2.3 | 9.7 km |
Solar Photovoltaics · Operational | 13 | 10.4 km |
How big is Langenhoe Solar Farm?
Langenhoe Solar Farm has a recorded installed capacity of 21.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Langenhoe Solar Farm?
REPD records the operator as NextEnergy Solar Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Langenhoe Solar Farm approved and built?
The application was submitted on 22 November 2013. Permission was granted on 29 August 2014, 9 months later. The site became operational on 4 March 2015, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1463.
Novarly Parcel · official public data, read properly · parcel.novarly.com