Renewable sites › Woden Park
Woden Park
Woden Park is an operational 5 MW solar farm in Vale of Glamorgan, generating since 26 March 2014. Planning permission was granted on 18 March 2013, 3 months after submission. Operator of record: Caerau Solar IQ.
Planning and build timeline
| Application submitted | 6 December 2012 |
| Permission granted | 18 March 2013 3 months after submission |
| Operational | 26 March 2014 12 months after consent |
Screening a site of your own?
Vale of Glamorgan approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Woden Park’s recorded coordinate — swap in your own postcode or coordinates.
Vale of Glamorgan’s record on solar
Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 3 | 3.5 km |
Solar Photovoltaics · Operational | 5 | 5 km |
Solar Photovoltaics · Operational | 6 | 6.3 km |
EfW Incineration · Operational | 30 | 6.5 km |
Sewage Sludge Digestion · Operational | 5.5 | 7 km |
Solar Photovoltaics · Operational | 7 | 7.1 km |
Advanced Conversion Technologies · Operational | 10 | 7.5 km |
Anaerobic Digestion · Operational | 2 | 7.5 km |
How big is Woden Park?
Woden Park has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Woden Park?
REPD records the operator as Caerau Solar IQ. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Woden Park approved and built?
The application was submitted on 6 December 2012. Permission was granted on 18 March 2013, 3 months later. The site became operational on 26 March 2014, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2096.