Novarly ParcelRenewable sites

Renewable sitesGriffin Wind farm

Griffin Wind farm

Griffin Wind farm is an operational 156 MW onshore wind farm in Scotland, generating since 28 February 2012. Planning permission was granted on 31 January 2008, 45 months after submission. Operator of record: Greenpower (Griffin) Ltd.

156 MW
Capacity
as recorded in REPD
Operational
Status
since 28 February 2012
Wind Onshore
Technology
Greenpower (Griffin) Ltd
National
Authority
Scotland

Planning and build timeline

Application submitted27 April 2004
Permission granted31 January 2008
45 months after submission
Operational28 February 2012
49 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Griffin Wind farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
1.18.8 km
Wind Onshore · Operational
32.210.2 km
Large Hydro · Operational
1513.1 km

How big is Griffin Wind farm?

Griffin Wind farm has a recorded installed capacity of 156 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Griffin Wind farm?

REPD records the operator as Greenpower (Griffin) Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Griffin Wind farm approved and built?

The application was submitted on 27 April 2004. Permission was granted on 31 January 2008, 45 months later. The site became operational on 28 February 2012, 49 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4028.