Planning and build timeline
| Application submitted | 12 June 2023 |
| Permission granted | 25 July 2023 1 months after submission |
| Operational | 1 May 2023 |
Screening a site of your own?
Perth and Kinross approves 82% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Blair Castle Caravan Park, Blair Atholl - Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
Perth and Kinross’s record on solar
Perth and Kinross has decided 22 solar farms and approved 82%, taking a median of 3.3 months. See every solar farm decision in Perth and Kinross →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 1.9 | 8.8 km |
Large Hydro · Operational | 15 | 10 km |
Large Hydro · Operational | 40 | 12.8 km |
Small Hydro · Operational | 1.1 | 13.9 km |
How big is Blair Castle Caravan Park, Blair Atholl - Solar Farm?
Blair Castle Caravan Park, Blair Atholl - Solar Farm has a recorded installed capacity of 0.16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blair Castle Caravan Park, Blair Atholl - Solar Farm?
REPD records the operator as Atholl Estates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blair Castle Caravan Park, Blair Atholl - Solar Farm approved and built?
The application was submitted on 12 June 2023. Permission was granted on 25 July 2023, 1 months later. The site became operational on 1 May 2023.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 14202.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode