Renewable sitesBattens Farm Solar Park

Battens Farm Solar Park

Battens Farm Solar Park is operational in Wiltshire with a recorded capacity of 11 MW, and has been generating since 2014-03-15.

11 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-15
Solar Photovoltaics
Technology
Battens Farm Solar Park Ltd
Wiltshire
Authority
England

Planning and build timeline

Application submitted2013-05-10
Permission granted2013-08-08
3 months after submission
Operational2014-03-15
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Leigh Delamere - Solar farm & Battery storage
Solar Photovoltaics · Under Construction
49.93 km
Leigh Delamere - Solar farm & Battery storage
Battery · Under Construction
403 km
Castle Combe Circuit
Solar Photovoltaics · Operational
123.9 km
Lake Farm
Solar Photovoltaics · Operational
55.5 km
Hullavington Solar Park
Solar Photovoltaics · Operational
76.8 km
Wick Farm Melksham Substation
Solar Photovoltaics · Under Construction
49.98.6 km
Wick Farm, Melksham Substation
Battery · Under Construction
8.6 km
Manor Farm (Wiltshire)
Solar Photovoltaics · Operational
6.38.9 km

How big is Battens Farm Solar Park?

Battens Farm Solar Park has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Battens Farm Solar Park?

REPD records the operator as Battens Farm Solar Park Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Battens Farm Solar Park approved and built?

The application was submitted on 2013-05-10. Permission was granted on 2013-08-08, 3 months later. The site became operational on 2014-03-15, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1476.