Renewable sitesHullavington Solar Park

Hullavington Solar Park

Hullavington Solar Park is an operational 7 MW solar farm in Wiltshire, generating since 3 February 2015. Planning permission was granted on 13 November 2013, 6 months after submission. Operator of record: Wessex Solar Energy.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 3 February 2015
Solar Photovoltaics
Technology
Wessex Solar Energy
Wiltshire
Authority
England

Planning and build timeline

Application submitted22 May 2013
Permission granted13 November 2013
6 months after submission
Operational3 February 2015
15 months after consent

Screening a site of your own?

RedlineUK · £39

Wiltshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hullavington Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
403.8 km
Solar Photovoltaics · Under Construction
49.93.8 km
Solar Photovoltaics · Operational
7.65 km
Solar Photovoltaics · Operational
126.6 km
Solar Photovoltaics · Operational
116.8 km
Solar Photovoltaics · Operational
57.2 km
Solar Photovoltaics · Operational
59.8 km
Solar Photovoltaics · Operational
7.210 km

How big is Hullavington Solar Park?

Hullavington Solar Park has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hullavington Solar Park?

REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hullavington Solar Park approved and built?

The application was submitted on 22 May 2013. Permission was granted on 13 November 2013, 6 months later. The site became operational on 3 February 2015, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2384.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode