Renewable sitesAcharn Forest Killin Biomass Plant

Acharn Forest Killin Biomass Plant

Acharn Forest Killin Biomass Plant is an operational 5.6 MW biomass plant in Stirling, generating since 15 July 2017. Planning permission was granted on 2 February 2015, 3 months after submission. Operator of record: Northern Energy Developments.

5.6 MW
Capacity
as recorded in REPD
Operational
Status
since 15 July 2017
Biomass (dedicated)
Technology
Northern Energy Developments
Stirling
Authority
Scotland

Planning and build timeline

Application submitted22 October 2014
Permission granted2 February 2015
3 months after submission
Operational15 July 2017
29 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Stirling: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Acharn Forest Killin Biomass Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Small Hydro · Operational
211.7 km
Large Hydro · Operational
1112.9 km
Small Hydro · Operational
214.8 km

How big is Acharn Forest Killin Biomass Plant?

Acharn Forest Killin Biomass Plant has a recorded installed capacity of 5.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Acharn Forest Killin Biomass Plant?

REPD records the operator as Northern Energy Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Acharn Forest Killin Biomass Plant approved and built?

The application was submitted on 22 October 2014. Permission was granted on 2 February 2015, 3 months later. The site became operational on 15 July 2017, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6061.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode