Renewable sitesArden Quarry Landfill

Arden Quarry Landfill

Arden Quarry Landfill is operational in High Peak with a recorded capacity of 3.1 MW, and has been generating since 2013-01-22.

3.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-01-22
Landfill Gas
Technology
Natural Power
High Peak
Authority
England

Planning and build timeline

Application submitted2002-01-23
Permission granted2002-12-18
11 months after submission
Operational2013-01-22
121 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Godley Water Treatment Works
Solar Photovoltaics · Operational
311.1 km
Bredbury Park Way - AD Stockport (Waste AD)
Anaerobic Digestion · Operational
211.5 km
Bredbury Substation - Battery Storage Facility
Battery · Under Construction
49.912 km
Welkin Road, Bredbury - Battery Storage System
Battery · Operational
2012.2 km
Welkin Mill, Welkin Road - Battery Storage
Battery · Under Construction
49.912.3 km
Waterswallows Road - Buxton Battery Storage Equipment
Battery · Operational
1512.5 km
Waterswallows Road - Buxton Battery Storage Equipment
Battery · Operational
1512.5 km
Denton Hall Farm Road, Denton - Solar Photovoltaic System
Solar Photovoltaics · Operational
1.1614 km

How big is Arden Quarry Landfill?

Arden Quarry Landfill has a recorded installed capacity of 3.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arden Quarry Landfill?

REPD records the operator as Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arden Quarry Landfill approved and built?

The application was submitted on 2002-01-23. Permission was granted on 2002-12-18, 11 months later. The site became operational on 2013-01-22, 121 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 783.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council