Renewable sites › Arbroath Battery Storage
Arbroath Battery Storage
Arbroath Battery Storage is an operational 35 MW battery storage site in Angus, generating since 2 April 2024. Planning permission was granted on 20 August 2019, 10 months after submission. Operator of record: Coronation Power / Persimmon Homes.
Planning and build timeline
| Application submitted | 23 October 2018 |
| Permission granted | 20 August 2019 10 months after submission |
| Operational | 2 April 2024 55 months after consent |
Screening a site of your own?
Angus approves 94% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Arbroath Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.
Angus’s record on battery storage
Angus has decided 18 battery storage schemes and approved 94%, taking a median of 6.2 months. See every battery storage scheme decision in Angus →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 4.7 km |
Solar Photovoltaics · Operational | 5 | 5.3 km |
Solar Photovoltaics · Operational | 10 | 5.6 km |
Solar Photovoltaics · Operational | 5 | 9.3 km |
Hydrogen · Under Construction | 0.8 | 9.9 km |
Wind Onshore · Under Construction | 1 | 9.9 km |
How big is Arbroath Battery Storage?
Arbroath Battery Storage has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Arbroath Battery Storage?
REPD records the operator as Coronation Power / Persimmon Homes. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Arbroath Battery Storage approved and built?
The application was submitted on 23 October 2018. Permission was granted on 20 August 2019, 10 months later. The site became operational on 2 April 2024, 55 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7163.