Novarly ParcelRenewable sites

Renewable sitesArbroath Battery Storage

Arbroath Battery Storage

Arbroath Battery Storage is an operational 35 MW battery storage site in Angus, generating since 2 April 2024. Planning permission was granted on 20 August 2019, 10 months after submission. Operator of record: Coronation Power / Persimmon Homes.

35 MW
Capacity
as recorded in REPD
Operational
Status
since 2 April 2024
Battery
Technology
Coronation Power / Persimmon Homes
Angus
Authority
Scotland

Planning and build timeline

Application submitted23 October 2018
Permission granted20 August 2019
10 months after submission
Operational2 April 2024
55 months after consent

Screening a site of your own?

RedlineUK · £39

Angus approves 94% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Arbroath Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Angus’s record on battery storage

Angus has decided 18 battery storage schemes and approved 94%, taking a median of 6.2 months. See every battery storage scheme decision in Angus

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
54.7 km
Solar Photovoltaics · Operational
55.3 km
Solar Photovoltaics · Operational
105.6 km
Solar Photovoltaics · Operational
59.3 km
Hydrogen · Under Construction
0.89.9 km
Wind Onshore · Under Construction
19.9 km

How big is Arbroath Battery Storage?

Arbroath Battery Storage has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arbroath Battery Storage?

REPD records the operator as Coronation Power / Persimmon Homes. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arbroath Battery Storage approved and built?

The application was submitted on 23 October 2018. Permission was granted on 20 August 2019, 10 months later. The site became operational on 2 April 2024, 55 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7163.

Novarly Parcel · official public data, read properly · parcel.novarly.com