Novarly ParcelRenewable sites

Renewable sitesWest Mains of Kinblethmont

West Mains of Kinblethmont

West Mains of Kinblethmont is operational in Angus with a recorded capacity of 5 MW, and has been generating since 2016-03-31.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-31
Solar Photovoltaics
Technology
BWE Partnership
Angus
Authority
Scotland

Planning and build timeline

Application submitted2015-05-18
Permission granted2015-09-04
4 months after submission
Operational2016-03-31
7 months after consent

Angus’s record on solar

Angus has decided 30 solar farms and approved 97%, taking a median of 4 months. See every solar farm decision in Angus

Other built sites within 15 km

SiteMWDistance
Parkhill Solar Farm
Solar Photovoltaics · Operational
51.3 km
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine
Hydrogen · Under Construction
0.84.8 km
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine
Wind Onshore · Under Construction
14.8 km
Arbroath Battery Storage
Battery · Operational
355.3 km
Pressock Farm
Solar Photovoltaics · Operational
56.8 km
New Mains Of Guynd Farm
Solar Photovoltaics · Operational
107.9 km

How big is West Mains of Kinblethmont?

West Mains of Kinblethmont has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Mains of Kinblethmont?

REPD records the operator as BWE Partnership. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Mains of Kinblethmont approved and built?

The application was submitted on 2015-05-18. Permission was granted on 2015-09-04, 4 months later. The site became operational on 2016-03-31, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5333.