Renewable sites › Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine is under construction in Angus with a recorded capacity of 0.8 MW.
Planning and build timeline
| Application submitted | 2022-02-03 |
| Permission granted | 2022-07-28 6 months after submission |
| Operational | not recorded |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine Wind Onshore · Under Construction | 1 | 0 km |
West Mains of Kinblethmont Solar Photovoltaics · Operational | 5 | 4.8 km |
Parkhill Solar Farm Solar Photovoltaics · Operational | 5 | 5.2 km |
Pressock Farm Solar Photovoltaics · Operational | 5 | 9.1 km |
Arbroath Battery Storage Battery · Operational | 35 | 9.9 km |
New Mains Of Guynd Farm Solar Photovoltaics · Operational | 10 | 12.4 km |
Stracathro Hospital Solar Solar Photovoltaics · Operational | 0.25 | 14.6 km |
How big is Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine?
Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine has a recorded installed capacity of 0.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine?
REPD records the operator as Arbikie Distillery. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Arbikie, Inverkeilor - Green Hydrogen Project & Wind Turbine approved and built?
The application was submitted on 2022-02-03. Permission was granted on 2022-07-28, 6 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11705.
Novarly Parcel · official public data, read properly · parcel.novarly.com