Renewable sites › Parkhill Solar Farm
Parkhill Solar Farm
Parkhill Solar Farm is an operational 5 MW solar farm in Angus, generating since 1 November 2018. Planning permission was granted on 3 February 2016, 3 months after submission. Operator of record: Innova / Lark Energy.
Planning and build timeline
| Application submitted | 2 November 2015 |
| Permission granted | 3 February 2016 3 months after submission |
| Operational | 1 November 2018 33 months after consent |
Screening a site of your own?
Angus approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Parkhill Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
Angus’s record on solar
Angus has decided 30 solar farms and approved 97%, taking a median of 4 months. See every solar farm decision in Angus →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 1.3 km |
Battery · Operational | 35 | 4.7 km |
Hydrogen · Under Construction | 0.8 | 5.2 km |
Wind Onshore · Under Construction | 1 | 5.2 km |
Solar Photovoltaics · Operational | 5 | 8.1 km |
Solar Photovoltaics · Operational | 10 | 8.3 km |
How big is Parkhill Solar Farm?
Parkhill Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Parkhill Solar Farm?
REPD records the operator as Innova / Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Parkhill Solar Farm approved and built?
The application was submitted on 2 November 2015. Permission was granted on 3 February 2016, 3 months later. The site became operational on 1 November 2018, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5914.