Novarly ParcelRenewable sites

Renewable sitesTrident Park

Trident Park

Trident Park is an operational 30 MW energy-from-waste plant in Cardiff, generating since 10 March 2015. Planning permission was granted on 29 June 2010, 5 months after submission. Operator of record: Viridor.

30 MW
Capacity
as recorded in REPD
Operational
Status
since 10 March 2015
EfW Incineration
Technology
Viridor
Cardiff
Authority
Wales

Planning and build timeline

Application submitted1 February 2010
Permission granted29 June 2010
5 months after submission
Operational10 March 2015
56 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Cardiff: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Trident Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
21.1 km
Sewage Sludge Digestion · Operational
5.51.5 km
Solar Photovoltaics · Operational
8.92.9 km
Landfill Gas · Operational
43.5 km
Solar Photovoltaics · Operational
1.53.8 km
Wind Onshore · Operational
2.35 km
Fuel Cell (Hydrogen) · Under Construction
0.116.3 km
Battery · Under Construction
1.086.3 km

How big is Trident Park?

Trident Park has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trident Park?

REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trident Park approved and built?

The application was submitted on 1 February 2010. Permission was granted on 29 June 2010, 5 months later. The site became operational on 10 March 2015, 56 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 922.

Novarly Parcel · official public data, read properly · parcel.novarly.com