Whiteside Hill is operational in Dumfries and Galloway with a recorded capacity of 25.3 MW, and has been generating since 2018-04-30.

25.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-04-30
Wind Onshore
Technology
Whiteside Hill Farm (Scotland)
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted2006-06-15
Permission granted2013-02-26
80 months after submission
Operational2018-04-30
62 months after consent

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Sanquhar Community Windfarm
Wind Onshore · Operational
32.41.8 km
Sandy Knowe Wind Farm
Wind Onshore · Operational
81.62.1 km
Sunnyside wind cluster
Wind Onshore · Operational
15.6 km
Sanquhar 2 Community Wind Farm
Battery · Under Construction
6.1 km
Sanquhar 2 Community Wind Farm
Wind Onshore · Under Construction
3086.1 km
Hare Hill (East Ayrshire)
Wind Onshore · Operational
13.26.2 km
Hare Hill Extension
Wind Onshore · Operational
29.86.2 km
Twentyshilling Hill Wind Farm
Wind Onshore · Under Construction
37.89.2 km

How big is Whiteside Hill?

Whiteside Hill has a recorded installed capacity of 25.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whiteside Hill?

REPD records the operator as Whiteside Hill Farm (Scotland). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whiteside Hill approved and built?

The application was submitted on 2006-06-15. Permission was granted on 2013-02-26, 80 months later. The site became operational on 2018-04-30, 62 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4502.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council