Renewable sites › Twentyshilling Hill Wind Farm
Twentyshilling Hill Wind Farm
Twentyshilling Hill Wind Farm is under construction in Dumfries and Galloway with a recorded capacity of 37.8 MW.
Planning and build timeline
| Application submitted | 2018-02-22 |
| Permission granted | 2019-12-23 22 months after submission |
| Operational | not recorded |
Dumfries and Galloway’s record on onshore wind
Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sunnyside wind cluster Wind Onshore · Operational | 1 | 7.3 km |
Whiteside Hill Wind Onshore · Operational | 25.3 | 9.2 km |
Sanquhar Community Windfarm Wind Onshore · Operational | 32.4 | 9.7 km |
Sanquhar 2 Community Wind Farm Battery · Under Construction | — | 11 km |
Sanquhar 2 Community Wind Farm Wind Onshore · Under Construction | 308 | 11 km |
Sandy Knowe Wind Farm Wind Onshore · Operational | 81.6 | 11.2 km |
Wether Hill Wind Onshore · Operational | 18.2 | 14.2 km |
How big is Twentyshilling Hill Wind Farm?
Twentyshilling Hill Wind Farm has a recorded installed capacity of 37.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Twentyshilling Hill Wind Farm?
REPD records the operator as Element Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Twentyshilling Hill Wind Farm approved and built?
The application was submitted on 2018-02-22. Permission was granted on 2019-12-23, 22 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6590.