Hare Hill Extension

Hare Hill Extension is operational in East Ayrshire with a recorded capacity of 29.8 MW, and has been generating since 2016-09-15.

29.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-15
Wind Onshore
Technology
Scottish Power Renewables
East Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted2007-09-04
Permission granted2014-11-28
87 months after submission
Operational2016-09-15
22 months after consent

East Ayrshire’s record on onshore wind

East Ayrshire has decided 20 onshore wind schemes and approved 45%, taking a median of 29.7 months. See every onshore wind scheme decision in East Ayrshire

Other built sites within 15 km

SiteMWDistance
Hare Hill (East Ayrshire)
Wind Onshore · Operational
13.20 km
Sandy Knowe Wind Farm
Wind Onshore · Operational
81.64.9 km
Sanquhar Community Windfarm
Wind Onshore · Operational
32.45.5 km
Whiteside Hill
Wind Onshore · Operational
25.36.2 km
Afton Wind Farm
Wind Onshore · Operational
506.5 km
Enoch Hill
Wind Onshore · Under Construction
706.9 km
Sanquhar 2 Community Wind Farm
Wind Onshore · Under Construction
3087 km
Sanquhar 2 Community Wind Farm
Battery · Under Construction
7 km

How big is Hare Hill Extension?

Hare Hill Extension has a recorded installed capacity of 29.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hare Hill Extension?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hare Hill Extension approved and built?

The application was submitted on 2007-09-04. Permission was granted on 2014-11-28, 87 months later. The site became operational on 2016-09-15, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4157.

Novarly Parcel · official public data, read properly · parcel.novarly.com