Planning and build timeline
| Application submitted | 2000-12-23 |
| Permission granted | 2002-06-19 18 months after submission |
| Operational | 2007-08-07 62 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on onshore wind
Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Arkleby Mill Anaerobic Digestion · Operational | 1 | 4.9 km |
Aspatria Creamery Anaerobic Digestion · Operational | 5 | 5.3 km |
Tallentire Hill Wind Onshore · Operational | 12 | 5.8 km |
Aspatria Solar Photovoltaics · Operational | 19 | 6.9 km |
M Sport, Dovenby Hall Estate - Solar Panels Solar Photovoltaics · Operational | 0.8 | 7.5 km |
Westnewton Wind Onshore · Operational | 6.2 | 7.8 km |
High Pow Farm Wind Onshore · Operational | 3.9 | 9.1 km |
How big is Wharrels Hill Wind Farm?
Wharrels Hill Wind Farm has a recorded installed capacity of 10.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wharrels Hill Wind Farm?
REPD records the operator as Wharrels Hill Windfarm Ltd/ National Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wharrels Hill Wind Farm approved and built?
The application was submitted on 2000-12-23. Permission was granted on 2002-06-19, 18 months later. The site became operational on 2007-08-07, 62 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2618.