Novarly ParcelRenewable sites

Renewable sitesHigh Pow Farm

High Pow Farm

High Pow Farm is operational in Cumberland with a recorded capacity of 3.9 MW, and has been generating since 2007-03-15.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2007-03-15
Wind Onshore
Technology
REG Windpower (previously Cornwall Light and Power)
Cumberland
Authority
England

Planning and build timeline

Application submitted2004-07-16
Permission granted2004-10-07
3 months after submission
Operational2007-03-15
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cumberland’s record on onshore wind

Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland

Other built sites within 15 km

SiteMWDistance
Aspatria
Solar Photovoltaics · Operational
198.6 km
Wharrels Hill Wind Farm
Wind Onshore · Operational
10.49.1 km
Aspatria Creamery
Anaerobic Digestion · Operational
59.6 km
Westnewton
Wind Onshore · Operational
6.210 km
Arkleby Mill
Anaerobic Digestion · Operational
110.1 km
Great Orton
Wind Onshore · Operational
411.7 km
Great Orton Wind Farm (Extension)
Wind Onshore · Operational
2.311.8 km
Hellrigg Wind farm
Wind Onshore · Operational
9.212.3 km

How big is High Pow Farm?

High Pow Farm has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates High Pow Farm?

REPD records the operator as REG Windpower (previously Cornwall Light and Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was High Pow Farm approved and built?

The application was submitted on 2004-07-16. Permission was granted on 2004-10-07, 3 months later. The site became operational on 2007-03-15, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4029.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council